daily samvaad visakhapatnam port 15 nov 2026 (1)

Visakhapatnam Port plans to mechanise five cargo berths under three operating contracts

Visakhapatnam, 11 November 2026 — Visakhapatnam Port plans to equip five existing cargo berths with cranes, conveyors and environmental controls under three operation and maintenance contracts. Union Ports Minister Sarbananda Sonowal laid the foundation stones on 11 November. The ministry expects the contracts to provide work for about 500 local people.

How the five berths are grouped

Two operators’ contracts each cover a pair of berths, WQ-1 with WQ-1RE and WQ-2 with WQ-3. The third covers EQ-3. Under each contract, the operator must install cargo-handling equipment and environmental controls as part of running the terminal. Sonowal said the port aims to secure a more predictable flow of cargo and make fuller use of the berths. The ministry did not give a commissioning date for the equipment.

Recycled water for dust control

Sonowal also laid the foundation stone for an estimated ₹11 crore sewage treatment upgrade. A new unit would add 5 million litres of daily capacity, taking the port’s total from 10 million to 15 million litres a day. The port already uses treated water to wet roads and suppress dust in cargo stockpile yards. The expansion forms part of the ministry’s Harit Sagar green port initiative.

The port handled a record 91.17 million tonnes of cargo in FY 2025–26. Between April and October 2026, it handled another 4.44 million tonnes more than in the same seven months a year earlier, an increase of 8.88%. For shippers, the significance of the berth contracts lies in how efficiently operators can move that growing volume through the existing waterfront.

Primary source · Ministry of Ports, Shipping and Waterways, 11 November 2026